Glow Energy Phase 2 N12.693739, E101.144439 GPS Location: 

 


Glow Energy Phase 2 Central Utilities Cogeneration Plant was developed by Glow Energy Public Co., Ltd., This plant, that began commercial operation in April 1996, employed a combined cycle cogeneration process for the purpose of utilizing natural gas (or diesel). This plant supplies electricity through a dedicated underground cable connection to industrial customers. Steam and water distribution systems directly supply with both high and medium pressure steams. Besides the industrial customers, the plant also supplies 180 MW of electricity to EGAT under Small Power Producer (SPP) program.

In addition, this plant also connects its electricity transmission system to Glow Phase 3&4 Hybrid Cogeneration Plant to strengthen overall transmission system reliability.

Plant Information
  • Name: Glow Energy Phase 2 Power Plant
  • Location: Map Ta Phut Industrial Estate, Rayong
  • Production Capacity: Power 281 MW, Steam 300 t/hr, Clarified water 900 cu.m./hr, Demineralized water 280 cu.m./hr
  • Commercial Operation Date: April 1996
  • Type of fuel: Natural gas
  • Tel: (66 38) 684 078-80
  • Fax: (66 38) 684 061